QUESTION 111
A stakeholder wants to make a change to the work breakdown structure that does NOT affect the time or cost of the project. What is the BEST thing to do?
A. Tell the stakeholder that this change cannot be made without revising the project management plan.
B. Make the change.
C. Meet with management.
D. Look for other impacts on the project.